BPM & BLM Upgrade Project
Fermilab Beams Division Beams Division BPM & BLM Upgrade Project Meetings

Fermilab at work Documents Telephone Organization Mailing Lists

Tevatron BPM Project Information

Project charge codes as of July 2005

Project FTE usage (time worked)

Purchase order tracking: TBPMWBS Ver 3, TBPMWBS Ver 2

Documents: Controlled (approved) and As-Built (final)

Project definition for CD project database

TBPM changes: BCA#3 document, BCA#3 cost

Project WBS Dictionary and Basis of Estimate Version 3.2

Requisition and purchase order creation and tracking procedure

All purchases for the Tevatron BPM upgrade project should be made using the AD charge code 20.26.4.6.4.0.2. All requisitions should be made using the Purchase Requisition form (MS Word doc) available at http://www-bss.fnal.gov/Procurement/index.html . Requesters from CD division should not use the requisition system internal to CD division. Please e-mail me (Bakul Banerjee) when you place the requisition.

Since Tevatron BPM procurement is significant, it is necessary to keep track of Purchase Orders (procard orders if applicable) for big and small items. To keep track of them within the project office, please make sure to forward Bakul the following:

  1. Quotes from vendors, particularly the final quotes
  2. AD requisitions signed by project managers along with all attachments
  3. Oracle Alerts you receive when the order is placed
  4. Oracle Alerts when the order is received.

Project file tracking procedure

  1. Creating: TBPM project file is created using an active dialog among project management team members, including L2 managers. First step is to create the Work Breakdown Structure using various sources. Next step is to assign duration and resources including availability and cost. For the TBPM project, an average SWF cost per job category prescribed in the RUNII Upgrade project file is assigned. Actual SWFs for individuals are not tracked currently. This may change later, as the project becomes more stable. All tasks are scheduled using "As Soon As possible" constraint types as default. Following task type assignment convention is used:
    • Reviews: Fixed duration with 1 day as default
    • Tasks other than reviews or summary tasks: Fixed work
    • Tasks involving PO/Procard: Material with fixed unit whenever applicable
  2. Tracking: Initial project file is refined and updated until it is baselined (as MSP baseline file) after approval by the project manager. Subsequent baselines are taken as determined by the project manager. After first baseline, status updates are made by the L2 managers on previously agreed upon dates. It is suggested that the L2 managers should update the status update spreadsheet on the project web using red color and e-mail the file to the project assistant. Project assistant is always available for consultation and assistance for status updates. Initially, status updates will occur frequently. Please note any new PO/Procard initiated should be noted on the status update reports.
  3. Change control: Once the project file is baselined, any major changes to the scope, schedule and cost should be brought to the attention of the project manager as soon as possible, so that these changes can be authorized properly.

Project Managers: Steve Wolbers (CD)/Bob Webber (AD)

Project Assistant: Bakul Banerjee

 

 

Last modified by BB  mailto:bakulb@fnal.gov